Construction businesses report widespread fuel and energy concerns
Around four in five construction businesses expressed concern about rising fuel prices in late October, while almost three-quarters were concerned about energy prices, according to the latest ONS figures.
Results published on 5 November 2026 show that 79.8% of construction businesses were somewhat or very concerned about increases in fuel prices, compared with 70.3% across all businesses surveyed. For energy prices, the proportions were 74.1% and 68.8%, respectively.
Sam Parkin, senior economist at BCIS, said: ‘Fuel and energy remain significant sources of concern for construction businesses. Their exposure extends beyond running vehicles and equipment on site, because energy and transport costs also feed into the manufacture and delivery of materials.
‘These responses measure businesses’ concerns rather than actual price increases, but they highlight the pressures contractors and clients need to consider when reviewing budgets, procurement plans and project viability.’
Fuel and energy concerns
Construction businesses were more likely than businesses across the survey as a whole to describe themselves as very concerned about fuel prices: 58.0% did so, compared with 38.1% across all businesses.
The proportion of construction businesses very concerned about energy prices was also higher, at 38.7%, compared with 30.6%.
| Concern in late October 2026 |
Construction |
All businesses |
| Fuel prices: very concerned |
58.0% |
38.1% |
| Fuel prices: somewhat concerned |
21.8% |
32.2% |
| Energy prices: very concerned |
38.7% |
30.6% |
| Energy prices: somewhat concerned |
35.4% |
38.2% |
Overall concern about both fuel and energy prices remained above late-August levels in construction, when 72.6% expressed concern about fuel prices and 58.5% about energy prices.
However, the latest estimates were lower than in early October, when the corresponding proportions were 85.4% and 75.3%.
Materials costs lead supply chain expectations
Among construction businesses that reported on their supply chain concerns, 68.2% expected those factors to increase the cost of sourcing materials. This compared with 53.5% across all businesses answering the question.
More than half of construction businesses in this group, 56.5%, expected increased transportation costs. A further 28.4% anticipated shortages of inputs, while 27.6% expected increased labour costs.
| Expected supply chain effect |
Construction |
All businesses |
| Increased cost of sourcing materials |
68.2% |
53.5% |
| Increased transportation costs |
56.5% |
52.0% |
| Shortage of inputs |
28.4% |
22.9% |
| Increased labour costs |
27.6% |
21.5% |
Note: These percentages relate to businesses reporting on supply chain concerns, rather than all businesses. Respondents could select more than one effect.
The construction estimate for increased materials sourcing costs was below the 73.2% recorded in the previous survey covering these questions. The proportion anticipating shortages of inputs was higher, at 28.4%, compared with 22.7%.
‘The Middle East war continues to weigh heavily on the construction sector,’ Parkin said. ‘Key materials, for instance, diesel and aluminium, remain elevated due to the war. Transportation costs are greater due to higher diesel costs but also insurance costs. Additionally, the construction industry also faces greater costs from steel, which is more regulated, and copper, which faces increased demand, both of which are key materials for the construction sector.
‘Low demand also remains a key concern. Contractors are unable to pass on greater costs, meaning margins are squeezed. Aggressive pricing strategies only increase risk, resulting to contractors having to balance viability with eagerness to tender.’
Conflict and shipping remain concerns
Over the next 12 months, 20.2% of construction businesses identified international conflict as a concern for supply chains, while 18.1% cited shipping disruption and 14.8% increased barriers to trade.
Around half, 50.7%, said they were not concerned about the listed factors affecting supply chains.
Parkin said: ‘The potential effects on materials sourcing and transport are particularly relevant to construction. Even firms that buy through UK suppliers can be exposed to disruption further along the supply chain.
‘Understanding where key products come from, checking lead times and keeping cost allowances under review can help project teams respond before higher costs or shortages affect delivery.’
To keep up to date with the latest industry news and insights from BCIS, register for our newsletter here.